Question: For a given network with the information in the table, do the following (first activity is A, last activity is R): a. Draw the arrow

For a given network with the information in the table, do the following (first activity is A, last activity is R):

a. Draw the arrow diagram. b. Find the earliest time the project can be completed using the CPM method. c. Calculate the Total Abundance values. D. What are the critical activities? Show the critical path (use activity names) and explain its meaning.

Event Event Duration (days)

For a given network with the information in the

0-1 1-2 1-3 2-5 2-4 3-4 3-7 3-6 5-8 2-7 4-7 6-7 6-8 7-8 8-9 524+ 8 6 8 3 9 4 5 5 13 4 6