Question: For a project, the T01: = $200,000, the CE'v = $100,000, the (IN: = $120,000. Which of the following Statements. is. true? O The FCAC

 For a project, the T01: = $200,000, the CE'v" = $100,000,

the (IN: = $120,000. Which of the following Statements. is. true? O

For a project, the T01: = $200,000, the CE'v" = $100,000, the (IN: = $120,000. Which of the following Statements. is. true? O The FCAC i5 Ie55 than the budget and the project scope should be adjuated. O The project i5 progresaing well and should be continued. O The CPI is more than 1.0. Q The project has a negative co5t variance and corrective action is needed