Question: For a project with three tasks, the start dates, end dates, and budget are as follows: TASK ID END DATE June 20th 1 2
For a project with three tasks, the start dates, end dates, and budget are as follows: TASK ID END DATE June 20th 1 2 June 25th 3 June 30th START DATE June 1st June 7th June 10th BUDGET $10,000 $15,000 $20,000 Assume that the date is June 15th and Tasks 1, 2, and 3 are 60%, 80%, and 25% complete, respectively. Determine the Schedule Performance Index for each task, and for the project overall.
Step by Step Solution
3.38 Rating (170 Votes )
There are 3 Steps involved in it
The Schedule Performance Index SPI measures the efficiency of project schedule performance It is cal... View full answer