Question: For a selected project following calculation were estimated by a project manager: State of the Probability Projected NPV Economy Recession 0.6 12,000 Stable 0.4 15,000

 For a selected project following calculation were estimated by a project

For a selected project following calculation were estimated by a project manager: State of the Probability Projected NPV Economy Recession 0.6 12,000 Stable 0.4 15,000 Growing 0.2 22,000 Calculate the Ev value of the above project with the given information Select one: O A. OMR 31,400 B. OMR 17,600 O C. OMR 49,000 O D. None of the given options