Question: For an activity in a CPM analysis the Early Start time is 1 5 and the Late Start time is 2 0 . Which of
For an activity in a CPM analysis the Early Start time is and the Late Start time is Which of the following statements is true?
Question options:
a
The activity is not on the critical path.
b
The duration of this task is
c
The slack for this activity is
d
The activity's late start must happen before its early start.