Question: For an activity in a critical path model (CPM) analysis, the early start time is 6 and the late start time is 11. Which of

 For an activity in a critical path model (CPM) analysis, the

For an activity in a critical path model (CPM) analysis, the early start time is 6 and the late start time is 11. Which of the following statements is true? Multiple Choice O The Early Finish is 10 The activity is on the critical path O The slack for this activity is 2 None of them The Late Finish is 12