Question: For an activity in a critical path model (CPM) analysis, the early start time is 6 and the late start time is 11. Which of

For an activity in a critical path model (CPM)
For an activity in a critical path model (CPM) analysis, the early start time is 6 and the late start time is 11. Which of the following statements is true? Multiple Choice The Late Finish is 12 The Early Finish is 10 The slack for this activity is 2 O None of them The activity is on the critical path