Question: For an activity in a Single Time Estimate CPM analysis the Early Finish time is 2 0 and the Late Finish time is 2 0

For an activity in a Single Time Estimate CPM analysis the Early Finish time is 20 and the Late Finish time is 20. Which of the following statements is true?
The activity's late start must happen before its early start
The activity is on the critical path
The slack for this activity is 20
The duration of this task is zero
The duration of this task is 20
 For an activity in a Single Time Estimate CPM analysis the