Question: Question 3 1 Point For an activity in a Single Time Estimate CPM analysis, the Early Finish time is 8 and the Late Finish time

Question 3
1
Point
For an activity in a Single Time Estimate CPM analysis, the Early Finish time is 8 and the Late Finish time is 10. Which of the following statements is true?
The slack for this activity is 2
The Early Finish is 10
The activity is on the critical path
The duration of this activity is 2
The Late Finish is 12