Question: For an activity in a Single Time Estimate CPM analysis the Early Finish time is 20 and the Late Finish time is 20/Which of the

For an activity in a Single Time Estimate CPM analysis the Early Finish time is 20 and the Late Finish time is 20/Which of the following statements is true? The duration of this activity is 20 O The activity's late start must happen before its early start O The duration of this activity is zero O The slack for this activity is 20 O The activity is on the critical path