Question: For an imaginary software development project the top level Work Breakdown Structure ( WBS ) looks like this: All duration estimates are in days, and
For an imaginary software development project the top level Work Breakdown Structure WBS looks like this:
All duration estimates are in days, and the network proceeds from Activity A to Activity H
Assume a day work week.
Draw a simple activityonnode AoN network diagram representing the project.
How many paths are possible?
Show, or identify the activities for the Critical Path of this project? How many days?
Which activities demonstrate Slack time?
What is the shortest possible time, in weeks, it will take to complete this project?For an imaginary software development project the top level Work Breakdown Structure WBS looks like this:
Activity Description
Preceding Activity
Optimistic Realistic Pessimistic
A Define Requirements None
B Assign Team A
C Design Software B
D Code Software B
E Test Software D
F Develop Patent Request C E
G Build Deployment Package D
H Deploy to Client E F G
All duration estimates are in days, and the network proceeds from Activity A to Activity H
Assume a day work week.
Draw a simple activityonnode AoN network diagram representing the project.
How many paths are possible?
Show, or identify the activities for the Critical Path of this project? How many days?
Which activities demonstrate Slack time?
What is the shortest possible time, in weeks, it will take to complete this project?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock