Question: For below questions, suppose we have these project tasks, A , estimated time 5 days B , estimated time 2 days, depends on A ,

For below questions, suppose we have these project tasks,
A, estimated time 5 days
B, estimated time 2 days, depends on A,C
C, estimated time 7 days
D, estimated time 4 days, depends on B
E, estimated time 3 days, depends on D
G, estimated time 2 days, depends on B
H, estimated time 4 days, depends on G
I, estimated time 2 days, depends on H
F, estiamted time 4 days, depends on E, I
J, estimated time 5 days, depends on F
What's the critical path? How long is it?
The development of task C goes quicker than expected, and is complete within 2 days. What's the new critical path and its length?
Task D took 8 days to complete instead of estimated 4. What's the new critical path and its length?
What's the difference between risk and uncertainty?
Give three examples of risk.
Give three examples of uncertainty?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!