Question: For below questions, suppose we have these project tasks, A , estimated time 5 days B , estimated time 2 days, depends on A ,
For below questions, suppose we have these project tasks,
A estimated time days
B estimated time days, depends on AC
C estimated time days
D estimated time days, depends on B
E estimated time days, depends on D
G estimated time days, depends on B
H estimated time days, depends on G
I, estimated time days, depends on H
F estiamted time days, depends on E I
J estimated time days, depends on F
What's the critical path? How long is it
The development of task C goes quicker than expected, and is complete within days. What's the new critical path and its length?
Task D took days to complete instead of estimated What's the new critical path and its length?
What's the difference between risk and uncertainty?
Give three examples of risk.
Give three examples of uncertainty?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock