Question: For below questions, suppose we have these project tasks, A , estimated time 5 days B , estimated time 2 days, depends on A ,

For below questions, suppose we have these project tasks,
A, estimated time 5 days
B, estimated time 2 days, depends on A,C
C, estimated time 7 days
D, estimated time 4 days, depends on B
E, estimated time 3 days, depends on D
G, estimated time 2 days, depends on B
H, estimated time 4 days, depends on G
I, estimated time 2 days, depends on H
F, estiamted time 4 days, depends on E, I
J, estimated time 5 days, depends on F
What's the critical path? How long is it?
The development of task C goes quicker than expected, and is complete within 2 days. What's the new critical path and its length?
Task D took 8 days to complete instead of estimated 4. What's the new critical path and its length?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!