Question: For below questions, suppose we have these project tasks, A , estimated time 5 days B , estimated time 2 days, depends on A ,
For below questions, suppose we have these project tasks,
A estimated time days
B estimated time days, depends on AC
C estimated time days
D estimated time days, depends on B
E estimated time days, depends on D
G estimated time days, depends on B
H estimated time days, depends on G
I, estimated time days, depends on H
F estiamted time days, depends on E I
J estimated time days, depends on F
What's the critical path? How long is it
The development of task C goes quicker than expected, and is complete within days. What's the new critical path and its length?
Task D took days to complete instead of estimated What's the new critical path and its length?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock