Question: For conventional work groups, Blank _ _ _ _ _ _ is the last stage of their development. However, for project teams, there is a
For conventional work groups, Blank is the last stage of their development. However, for project teams, there is an Blank phase where attention is devoted to wrapping up the project.
Multiple choice question.
performing; adjourning
norming; acceptance
validation; audit
performing; validation
lessons learned; operations