Question: For Part 2 of the Final Project, develop a baseline for this project using the project management software tool identified in Part 1. Enter the
For Part 2 of the Final Project, develop a baseline for this project using the project management software tool identified in Part 1.
Enter the activities, durations and predecessors under Normal conditions. Put either your Microsoft Project file or pics of your Tasks/Milestones, Predecessor assignments, and Network Diagram chart (put into a Word document) in the Final Project Part 1 drop box. Name the file as: LastName_FirstName_Part_2.
Identify the Critical path in your initial network diagram.
When completed, submit this part of the Final Project to the Final Project Part 2 drop box
BA 421 Race for Memory
| Activity | Description | Predecessors | Normal Time in Days | Normal Time Cost |
| 1 | Finalize sites & contracts |
| 28 | $10,000 |
| 2 | Select race promoter | 1 | 14 | $7,500 |
| 3 | Hire Race Manager | 2 | 21 | $5,000 |
| 4 | Design Promotional Website | 2 | 25 | $10,000 |
| 5 | Target entertainment | 2 | 45 | $12,500 |
| 6 | Set venue capacity | 3 | 3 | $2,000 |
| 7 | Identify On-site fundraising | 3 | 6 | $1,500 |
| 8 | Finalize sponsors | 7 | 35 | $9,000 |
| 9 | Define & place signage for sponsors | 8 | 8 | $3,000 |
| 10 | Sign Concession Contracts | 2 | 32 | $8,000 |
| 11 | Secure Merchandise sales | 7 | 25 | $6,100 |
| 12 | Purchase Race awards | 2 | 48 | $5,500 |
| 13 | Develop site plan | 6, 10 | 31 | $9,000 |
| 14 | Hire Security Director | 2 | 20 | $4,200 |
| 15 | Hire Support Staff | 2 | 17 | $3,600 |
| 16 | Develop police/fire security plan | 14 | 55 | $10,000 |
| 17 | Develop Traffic Plan | 13 | 20 | $9,500 |
| 18 | Determine Reqmts for Power & Facilities | 13 | 30 | $6,200 |
| 19 | Install Power/plumbing/AC/Toilet Svcs | 18 | 6 | $9,500 |
| 20 | Ready for Race | 15, 16, 17, 19 | 1 |
|