Question: * (For problems from 8 to 10.) The activities information for a project is given as below. Indirect costs are $10,000 per week, and a

* (For problems from 8 to 10.) The activities
* (For problems from 8 to 10.) The activities
* (For problems from 8 to 10.) The activities information for a project is given as below. Indirect costs are $10,000 per week, and a penalty cost of $10,000 per week will be incurred for every week past week 9 until the project is completed. Immediate Predecessor(s) Activity A B Time (weeks) Normal Crash 3 2 1 1 4 2 Cost ($) Normal Crash 7,000 10,000 3,000 3,000 12,000 40,000 SEE N-N A D E 2 6 B DE E 1 2 12,000 8,000 5,000 9,000 4 2 28,000 8,000 15,000 18,000 G 8. What is the shortest time duration for this project, regardless of the cost? A. less than 8 weeks B. 8 weeks C. 9 weeks D. more than 9 weeks 9. What is the total cost associated with completing the project in 12 weeks? A. less than or equal to $160,000 B. greater than $160,000 but less than or equal to $200,000 C. greater than $200,000 but less than or equal to $240,000 D. greater than $240,000 10. What will be the total time of the minimum-cost schedule? A. 8 weeks or less B. 9 weeks C. 10 weeks D. 11 weeks or more

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!