Question: For revision - Project Mgmt Consider the table below: Activities Predecessor Optimistic Most Likely Pessimistic A 2 4 12 B 9 9 9 C A
For revision - Project Mgmt
Consider the table below:
| Activities | Predecessor | Optimistic | Most Likely | Pessimistic |
| A |
| 2 | 4 | 12 |
| B |
| 9 | 9 | 9 |
| C | A | 10 | 12 | 26 |
| D | A | 8 | 9 | 10 |
| E | B, C | 10 | 15 | 20 |
| F | D | 9 | 9 | 9 |
| G | D, E, F | 3 | 3.5 | 7 |
a). Calculate the duration for each activity using the information from the table above.
b). Prepare a schedule network diagram, for the above project showing the early start, early finish, late start, late finish and slack.