Question: For revision - Project Mgmt Consider the table below: Activities Predecessor Optimistic Most Likely Pessimistic A 2 4 12 B 9 9 9 C A

For revision - Project Mgmt

Consider the table below:

Activities

Predecessor

Optimistic

Most Likely

Pessimistic

A

2

4

12

B

9

9

9

C

A

10

12

26

D

A

8

9

10

E

B, C

10

15

20

F

D

9

9

9

G

D, E, F

3

3.5

7

a). Calculate the duration for each activity using the information from the table above.

b). Prepare a schedule network diagram, for the above project showing the early start, early finish, late start, late finish and slack.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!