Question: For the activities shown in the table below, please indicate the path. Immediate Activity Duration (days) Predecessors 10 B 00 C 2 A D E

For the activities shown in the table below,For the activities shown in the table below,

For the activities shown in the table below, please indicate the path. Immediate Activity Duration (days) Predecessors 10 B 00 C 2 A D E B,C,D B-E O A-C-E O A-D-E For the activities shown in the table below, please indicate the project completion time. Immediate Activity Duration (days) Predecessors 10 B 8 --- 2 A D 4 A E 5 B,C,D 5 days 19 days 6 days