Question: For the activities shown in the table below, please indicate the critical path. Activity Duration Immediate ( days ) Predecessors A 1 0 B 8

For the activities shown in the table below, please indicate the critical path.
Activity
Duration
Immediate
(days)
Predecessors
A
10
B
8
C
2
A
D
4
A
E
5
B,C,D
B-E
A-C-E
A-D-E
 For the activities shown in the table below, please indicate the