Question: For the determine data needs activity of a project, the optimistic estimated duration is 10 days, the pessimistic estimated duration is 20 days, the most
For the "determine data needs" activity of a project, the optimistic estimated duration is 10 days, the pessimistic estimated duration is 20 days, the most likely time is 15 days. What is the expec