Question: Question 36 For one critical path activity within a project, the optimistic estimated duration is 10 days, but the project manager allows 15 days for
Question 36 For one critical path activity within a project, the optimistic estimated duration is 10 days, but the project manager allows 15 days for this activity in his schedule. This means that the project manager is incorporating no deadline for this activity 5 days of slack time Ono WBS for this activity O an additional milestone