Question: For one critical path activity within a project, the optimistic estimated duration is 10 days, but the project manager allows 15 days for this activity

For one critical path activity within a project, the optimistic estimated duration is 10 days, but the project manager allows 15 days for this activity in his schedule. This means that the project manager is incorporating _____. Group of answer choices no deadline for this activity 5 days of slack time no WBS for this activity an additional milestone