Question: For the following project a) Draw the network b) Calculate the expected time for each activity c) Calculate the ES, EF, LS, LF, the slack

For the following project a) Draw the network b)
For the following project a) Draw the network b) Calculate the expected time for each activity c) Calculate the ES, EF, LS, LF, the slack for each activity and identify the critical path d) Calculate the probability that the project will be completed by 13 weeks. e) Calculate the probability that the project will be completed by 17 weeks. Node Nos. Predecessor(s) 1 2 3 4 5 6 7 8 1 1 1 2 2,3,4 2 Shortest likely Time 1 5 3 1 2 4 1 1 Most likely Time 2 6 4 2 4 5 3 2 Longest Likely Time 3 7. 5 3 6 6 5 3 5,6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!