Question: Given the following project: Activity Predecessor Normal Time (day) Normal Cost ($) Crash Time (day) Crash Cost ($) A - 10 5000 10 5000 B

Given the following project:

Activity

Predecessor

Normal Time (day)

Normal Cost

($)

Crash Time (day)

Crash Cost

($)

A

-

10

5000

10

5000

B

-

12

1200

11

1300

C

A,B

11

3600

9

4800

D

C

5

300

4

600

E

C

8

1000

6

2000

F

C

9

2400

7

5400

(b) Calculate the maximum time reduction and crash cost-per-day (all activities may be partially crashed) for each activity. Then fill the table below.

Activity

Maximum Time Reduction (day)

Cost to Crash per Period ($/day)

A

B

C

D

E

F

G

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!