Question: Given the following project: Activity Predecessor Normal Time (day) Normal Cost ($) Crash Time (day) Crash Cost ($) A - 10 5000 10 5000 B
Given the following project:
| Activity | Predecessor | Normal Time (day) | Normal Cost ($) | Crash Time (day) | Crash Cost ($) |
| A | - | 10 | 5000 | 10 | 5000 |
| B | - | 12 | 1200 | 11 | 1300 |
| C | A,B | 11 | 3600 | 9 | 4800 |
| D | C | 5 | 300 | 4 | 600 |
| E | C | 8 | 1000 | 6 | 2000 |
| F | C | 9 | 2400 | 7 | 5400 |
|
|
(b) Calculate the maximum time reduction and crash cost-per-day (all activities may be partially crashed) for each activity. Then fill the table below.
| Activity | Maximum Time Reduction (day) | Cost to Crash per Period ($/day) |
| A |
|
|
| B |
|
|
| C |
|
|
| D |
|
|
| E |
|
|
| F |
|
|
| G |
|
|