Question: For the following project: Activity Predecessors Duration A None 7 B A SF: LT=2 13 C B FF: LT=3 6 D C FS: LT=1 16

For the following project: Activity Predecessors Duration A None 7 B A SF: LT=2 13 C B FF: LT=3 6 D C FS: LT=1 16 E A SF: LT=3 19 F B FF: LT=4, E FF: LT=5 18 G C FS: LT=4, F FS: LT=4 13 H D SS: LT=4, G SS: LT=5 8 E FF: LT=6 5 J F FS: LT=1, I FS: LT=5 10 K G SS: LT=6, J SS: LT=7 13 L H SF: LT=2, K SF: LT=3 11 Draw a precedence diagram and calculate the earliest start time, earliest finish time, latest start time, latest finish time, free float and total float for each activity. Use the following applet to answer the