Question: Given the following information regarding a project: Activity Predecessors Duration a None 3 b None 6 c None 8 d a 7 e b 5

Given the following information regarding a project:
Activity
Predecessors
Duration
a
None
3
b
None
6
c
None
8
d
a
7
e
b
5
f
c
10
g
c
4
h
d,e,f
5
i
g
6
14. Which of the following is NOT a path in the network?
a-d-h
b-e-h
c-f-h
c-g-i
c-g-h
15. What is the critical path?
a-d-h
b-e-h
c-f-h
c-g-i
c-g-h
16. How long will it take to complete the project?
15
16
18
23
25
17. What is the LS for activity c?
0
3
6
7
8
18. What is the LF for activity h?
13
17
18
23
19 What is the EF for activity h?
8
12
13
18
23
20. What is the LF for activity i?
8
12
13
18
23

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!