Question: Given the following information regarding a project: Activity Predecessors Duration a None 3 b None 6 c None 8 d a 7 e b 5
Given the following information regarding a project:
Activity
Predecessors
Duration
a
None
b
None
c
None
d
a
e
b
f
c
g
c
h
def
i
g
Which of the following is NOT a path in the network?
adh
beh
cfh
cgi
cgh
What is the critical path?
adh
beh
cfh
cgi
cgh
How long will it take to complete the project?
What is the LS for activity c
What is the LF for activity h
What is the EF for activity h
What is the LF for activity i
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock