Question: For the following project, what is the expected duration for Activity B ? ACTIVITY A B C D E F G H a 3 DAYS
For the following project, what is the expected duration for Activity B
ACTIVITY
A
B
C
D
E
F
G
H
a
DAYS
m
IMMEDIATE
PREDECESSORS
w
b
A
A
B C
D
D
D
F G
E F H
a
b
C
d