Question: For the following project, what is the expected duration for Activity B ? table [ [ , DAYS,IMMEDIATE ] , [ ACTIVITY , a

For the following project, what is the expected duration for Activity B?
\table[[,DAYS,IMMEDIATE],[ACTIVITY,a,m,b,PREDECESSORS],[A,3,6,6,-],[B,5,8,11,A],[C,5,6,10,A],[D,1,2,6,B, C],[E,7,11,15,D],[F,7,9,14,D],[G,6,8,10,D],[H,3,4,8,F, G],[I,3,5,7,E, F, H]]
a.336
b.156
C.396
d.486