Question: Given the following information. Construct a network diagram and answer the following questions: Critical Path: [Select] Total Duration: [Select] Activity B has (Select ] days

Given the following information. Construct a

Given the following information. Construct a network diagram and answer the following questions: Critical Path: [Select] Total Duration: [Select] Activity B has (Select ] days of Float Activity Duration (Days) Depends on 5 . B 11 A 9 A D 7 A E 14 A F 21 G 15 C,D B,F E,G H 8