Question: For the project data shown below, answer the following questions: a) Draw the activity network b) Perform forward and backward path calculations c) Show the

For the project data shown below, answer the following questions:

a) Draw the activity network

b) Perform forward and backward path calculations

c) Show the critical path

Activity Duration Immediate predecessor
A 10 -
B 30 A
C 15 B, D
D 20 -
E 3 C
F 2 E
G 10 F
H 5 C
I 5 All