Question: For the project data shown below, answer the following questions: a) Draw the activity network b) Perform forward and backward path calculations c) Show the
For the project data shown below, answer the following questions:
a) Draw the activity network
b) Perform forward and backward path calculations
c) Show the critical path
| Activity | Duration | Immediate predecessor |
| A | 10 | - |
| B | 30 | A |
| C | 15 | B, D |
| D | 20 | - |
| E | 3 | C |
| F | 2 | E |
| G | 10 | F |
| H | 5 | C |
| I | 5 | All |