Question: For the project network described in Question 8 , the critical path and project duration for the process is: A-B-C-D-E.F and 26 A-B-D-F and 16
For the project network described in Question 8 , the critical path and project duration for the process is: A-B-C-D-E.F and 26 A-B-D-F and 16 A.C-D.F and 13 A-C-E-F and 15