Question: For the project network described in Question 8 , the critical path and project duration for the process is: A - C - D -

For the project network described in Question 8,
the critical path and project duration for the process is:
A-C-D-F and 13
A-B-C-D-E-F and 26
A-C-E-F and 15
A-B-D-F and 16