Question: For the project network described in Question 8, the critical path and project duration for the process is: A-C-D-F and 13 A-B-D-F and 16 A-B-C-D-E-F


For the project network described in Question 8, the critical path and project duration for the process is: A-C-D-F and 13 A-B-D-F and 16 A-B-C-D-E-F and 26 A-C-E-F and 15 An activity on the project network has a slack time of 2 days. Which of the following is NOT true? Increasing the activity time by 2 days would decrease its slack time by 2 days. Increasing the activity time by 2 days would increase its slack time by 2 days. Increaseing the activity time by more than 2 days would increase the project duration. Increasing the activity time by 2 days would make this activity critical for the project