Question: For the project with Earned Value (EV) = $360, Actual Cost (AC) = $400 and both Cost Performance Index (CPI). The original project budget is

For the project with Earned Value (EV) = $360,
For the project with Earned Value (EV) = $360, Actual Cost (AC) = $400 and both Cost Performance Index (CPI). The original project budget is $1,000. Assuming the remaining work will NOT be impacted by the current cost performance and current schedule performance, what is the Estimate At Completion ($EAC) of the project? a) 1040 O b) 1111 b c) 1000 O d) 1100

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!