Question: For the project with Earned Value ( EV ) = $ 3 6 0 , Actual Cost ( AC ) = $ 4 0 0

For the project with Earned Value (EV)= $360, Actual Cost (AC)= $400. The original project budget is $1,000. Assuming the remaining work will be impacted by the current cost performance and current schedule performance, what is the Estimate At Completion ($EAC) of the project?
Question 17 options:
a)
1100
b)
1111
c)
1040
d)
1000