Question: For theproject withEarned Value (EV) = $360, Actual Cost (AC) = $400 and both Cost Performance Index (CPI) and Schedule Performance Index (SPI) equal 0.90.

For theproject withEarned Value (EV) = $360, Actual Cost (AC) = $400 and both Cost Performance Index (CPI) and Schedule Performance Index (SPI) equal 0.90. The originalproject budget is $1,000. Assuming the remaining work will be impacted bythecurrent cost performance and current schedule performance, what is the Estimate At Completion (EAC) of the project?

solve with the full explanation?