Question: For theproject withEarned Value (EV) = $360, Actual Cost (AC) = $400 and both Cost Performance Index (CPI) and Schedule Performance Index (SPI) equal 0.90.
For theproject withEarned Value (EV) = $360, Actual Cost (AC) = $400 and both Cost Performance Index (CPI) and Schedule Performance Index (SPI) equal 0.90. The originalproject budget is $1,000. Assuming the remaining work will be impacted bythecurrent cost performance and current schedule performance, what is the Estimate At Completion (EAC) of the project?
solve with the full explanation?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
