Question: For the project with the activates and costs given below Probability that the project could finish in 31 days 95% confidence for project completion time
- For the project with the activates and costs given below
- Probability that the project could finish in 31 days
- 95% confidence for project completion time
| Activity | Predecessor | Optimistic Duration | Normal Duration | Pesimistic Duration | Normal Cost | Crash time | Crash Cost |
| A | NA | 4 | 5 | 6 | $ 300.00 | 5 | $ 300.00 |
| B | A | 5 | 8 | 9 | $ 250.00 | 5 | $ 400.00 |
| C | A | 2 | 2 | 3 | $ 100.00 | 2 | $ 100.00 |
| D | A | 3 | 6 | 7 | $ 300.00 | 3 | $ 600.00 |
| E | B,C | 2 | 3 | 5 | $ 150.00 | 2 | $ 300.00 |
| F | C,D | 3 | 4 | 6 | $ 275.00 | 3 | $ 300.00 |
| G | E,F | 8 | 9 | 12 | $ 700.00 | 8 | $ 900.00 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock