Question: For the small warehouse below, the data is attached. The data include a list of activities and their durations. The activities are without any particular
For the small warehouse below, the data is attached. The data include a list of activities and their durations. The activities are without any particular order. Therefore, you are asked to do the following:
- Create the dependencies between activities.
- Using MS Project, draw a network and a bar chart for this project.
14 A small one-story commercial building is to be constructed on the site of an existing small frame structure. It is 30 ft by 60 ft in plan (see Figure Ex. 1.2). The exterior and interior walls are of concrete block. The roof is comprised of bar joists on long-span bar joists covered with a steel roof deck, rigid insulation, and built-up roofing. The ceiling is a suspended accoustical tile. The floor is a concrete slab on grade with an asphalt tile finish. Interior finish on all walls is paint. The project has been broken down into 18 steps and a construction time estimate has been made for each as follows. These steps are not in any particular order. Draw a bar chart for this project 1. Demolition-Including the demolition of the present structure, removal of debris, and rough grading of the site. Time: 2 days. 2. FoundationsThe construction of the foundation for the new structure. Time 3 days. 3. Underground Services-The installation of water and sewer service from main in the street. It is assumed that these services will be brought in under th structure within 30 ft width. Time: 1 day. 4. Exterior WallsThe construction of the exterior block walls. Time: 6 days. 5. Interior WallsThe construction of the interior block walls. Time: 3 days. 6. Roof SteelIncludes the installation of the long-span joists, the bar joists, and the steel roof deck. Time: 2 days. 7. Roof FinishIncludes the installation of the rigid insulation on the steel deck and the installation of the built-up roofing. Time: 2 days. 8. Floor SlabAssumed to include fine grading, sand fill and compaction, membrane waterproofing, casting and finishing of the floor slab. Time: 3 days. 9. Floor FinishIncludes the installation of asphalt tile and base mold. Time: 2 days. 10. Rough Plumbing and Heating-Includes the setting of the heating unit and rough ductwork, the installation of rough plumbing above the floor slab, vents, and so on. Time: 3 days. 11. Finish Plumbing and Heating-Includes the final installation of the heating radiators, controls, and so on, and the installation of the sink and water closet. Time: 4 days. 12. Rough ElectricalThe installation of conduit, service inlet and meter box, and so on. Time: 3 days. 13. Finish ElectricalThe installation of wire and fixtures. Time: 3 days. 14. Rough CarpentryThe installation of rough door frames, display window framing, and so on. Time: 2 days. 15. Finish Carpentry-The installation of door trim, hanging of doors, and so on. Time: 4 days. 16. Ceiling-The installation of the suspended acoustic ceiling. Time: 3 days. 17. Display WindowsThe installation of the display window glass and metal trim. Time: 1 day. 18. Paint-Painting of interior walls and trim. Time: 3 days. Although the har chart has achieved wide accente. Heat and mechanical Lavatory Storage Sales Figure Ex. 1.2 14 A small one-story commercial building is to be constructed on the site of an existing small frame structure. It is 30 ft by 60 ft in plan (see Figure Ex. 1.2). The exterior and interior walls are of concrete block. The roof is comprised of bar joists on long-span bar joists covered with a steel roof deck, rigid insulation, and built-up roofing. The ceiling is a suspended accoustical tile. The floor is a concrete slab on grade with an asphalt tile finish. Interior finish on all walls is paint. The project has been broken down into 18 steps and a construction time estimate has been made for each as follows. These steps are not in any particular order. Draw a bar chart for this project 1. Demolition-Including the demolition of the present structure, removal of debris, and rough grading of the site. Time: 2 days. 2. FoundationsThe construction of the foundation for the new structure. Time 3 days. 3. Underground Services-The installation of water and sewer service from main in the street. It is assumed that these services will be brought in under th structure within 30 ft width. Time: 1 day. 4. Exterior WallsThe construction of the exterior block walls. Time: 6 days. 5. Interior WallsThe construction of the interior block walls. Time: 3 days. 6. Roof SteelIncludes the installation of the long-span joists, the bar joists, and the steel roof deck. Time: 2 days. 7. Roof FinishIncludes the installation of the rigid insulation on the steel deck and the installation of the built-up roofing. Time: 2 days. 8. Floor SlabAssumed to include fine grading, sand fill and compaction, membrane waterproofing, casting and finishing of the floor slab. Time: 3 days. 9. Floor FinishIncludes the installation of asphalt tile and base mold. Time: 2 days. 10. Rough Plumbing and Heating-Includes the setting of the heating unit and rough ductwork, the installation of rough plumbing above the floor slab, vents, and so on. Time: 3 days. 11. Finish Plumbing and Heating-Includes the final installation of the heating radiators, controls, and so on, and the installation of the sink and water closet. Time: 4 days. 12. Rough ElectricalThe installation of conduit, service inlet and meter box, and so on. Time: 3 days. 13. Finish ElectricalThe installation of wire and fixtures. Time: 3 days. 14. Rough CarpentryThe installation of rough door frames, display window framing, and so on. Time: 2 days. 15. Finish Carpentry-The installation of door trim, hanging of doors, and so on. Time: 4 days. 16. Ceiling-The installation of the suspended acoustic ceiling. Time: 3 days. 17. Display WindowsThe installation of the display window glass and metal trim. Time: 1 day. 18. Paint-Painting of interior walls and trim. Time: 3 days. Although the har chart has achieved wide accente. Heat and mechanical Lavatory Storage Sales Figure Ex. 1.2