Question: For this assignment, you will utilize the SageKick project management software to develop resources for the following project details as specified below. This is an

For this assignment, you will utilize the SageKick project management software to develop resources for the following project details as specified below. This is an individual assignment. A project has been identified to contain the following list of activities along with their required times for completion:

Activity #

Activity

Time (Weeks)

Immediate Predecessors

1

Collect Requirements

2

-

2

Analyze Processes

3

1

3

Analyze Data

3

2

4

Design Processes

7

2

5

Design Data

6

2

6

Design Screens

1

3 & 4

7

Design Reports

5

4 & 5

8

Program

4

6 & 7

9

Test and Document

8

7

10

Install

2

8 & 9

Your tasks:

Make a new project for this assignment

Create the tasks as show in the table provided

The project start date should be January 31st, 2023

Calculate the earliest expected completion time (date and total weeks)

Create a Gantt chart with a critical path, save as a screenshot

What would happen if Activity #6 was revised to take 6 weeks instead of 1 week? What is the new expected completion time? (date and total weeks)

Create an updated Gantt chart with a critical path, save as a screenshot

Create a document with the information collected as specified below

To submit your work, share a document that includes the following information as either a PDF or shared link.

Your name

The date and duration for task 2B

Image of Gantt chart for task 2C

The date and duration for task 2D

Image of Gantt chart for task 2E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!