Question: For this assignment, you will utilize the SageKick project management software to develop resources for the following project details as specified below. This is an
For this assignment, you will utilize the SageKick project management software to develop resources for the following project details as specified below. This is an individual assignment. A project has been identified to contain the following list of activities along with their required times for completion:
| Activity # | Activity | Time (Weeks) | Immediate Predecessors |
| 1 | Collect Requirements | 2 | - |
| 2 | Analyze Processes | 3 | 1 |
| 3 | Analyze Data | 3 | 2 |
| 4 | Design Processes | 7 | 2 |
| 5 | Design Data | 6 | 2 |
| 6 | Design Screens | 1 | 3 & 4 |
| 7 | Design Reports | 5 | 4 & 5 |
| 8 | Program | 4 | 6 & 7 |
| 9 | Test and Document | 8 | 7 |
| 10 | Install | 2 | 8 & 9 |
Your tasks:
Make a new project for this assignment
Create the tasks as show in the table provided
The project start date should be January 31st, 2023
Calculate the earliest expected completion time (date and total weeks)
Create a Gantt chart with a critical path, save as a screenshot
What would happen if Activity #6 was revised to take 6 weeks instead of 1 week? What is the new expected completion time? (date and total weeks)
Create an updated Gantt chart with a critical path, save as a screenshot
Create a document with the information collected as specified below
To submit your work, share a document that includes the following information as either a PDF or shared link.
Your name
The date and duration for task 2B
Image of Gantt chart for task 2C
The date and duration for task 2D
Image of Gantt chart for task 2E