Question: For your project, you have broken down the work package into activities and just now completed the network diagram. Which process is this? a. Create

For your project, you have broken down the work package into activities and just now completed the network diagram. Which process is this? a. Create WBS b. Sequence activities c. Develop schedule d. Define schedule