Question: Forward Pass Computation Add activity times along each path in the network ( ES + Duration = EF ) . Carry the early finish (

Forward Pass Computation
Add activity times along each path in the network (ES + Duration = EF).
Carry the early finish (EF) to the next activity where it becomes its early start (ES) unless...
The next succeeding activity is a merge activity, in which case the largest early finish (EF) number of all its immediate predecessor activities is selected. Backward Pass Computation
Subtract activity times along each path starting with the project end activity (LF - Duration = LS).
Carry the late start (LS) to the next preceding activity where it becomes its late finish (LF) unless...
The next succeeding activity is a burst activity, in which case the smallest late start (LS) number of all its immediate successor activities is selected.
Total Slack )=(SL or )=(SL
Free Slack (FS)= Is the amount of time an activity can be delayed without delaying any immediately following (successor) activity.
 Forward Pass Computation Add activity times along each path in the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!