Question: Foundations: Incurred cost 2 4 0 0 , actual % complete 1 0 0 % Floor: Incurred cost 1 5 0 0 , actual %

Foundations: Incurred cost 2400, actual % complete 100%

Floor: Incurred cost 1500, actual % complete 100%

Building: Incurred cost 2700, actual % complete 50%

Electrical/Plumbing: Incurred cost 700 actual % complete 25%

Finishing: Incurred cost 0 actual % complete 0

With the above tables calculate the:

1. Actual value - AV (ACWP)

2. Earned value - EV (BCWP)

3. Planned value-PV (BCWS )

4. Cost performance index - CPI

5. Cost variance-CV

6. Scheduled performance index-SPI

7. Schedule variance



Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 Actual Value ACWP Sum of incurred costs ACWP 2400 1500 2700 700 0 ACWP 7300 2 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!