(FR) The Actual Costs (AC) to date are $12,000 and the Budget at Completion (BAC) for a project is $60,000. The Earned Value (EV) is $9,000. At this stage, the project management team did a manual bottom-up summation of costs and forecast an Estimate to Complete (ETC) of $54,000. What is the Estimate at Completion (EAC) for the project?
Correct Answer
a)
$66,000
b)
$72,000
Incorrect Response
c)
$80,000
d)
$63,000