Question: From an activity in a project, lntest start time is 8 weeks, latest finish time is 1 2 weeks. The slack time for the activity

From an activity in a project, lntest start time is 8 weeks, latest finish time is 12 weeks. The
slack time for the activity is
a)1 week
b)5 weeks
c)4 week
d) none of the above