Question: From the attached table, draw the network diagram. How long will it take 10 points to complete the project? Crash the project until the resources

From the attached table, draw the network

From the attached table, draw the network diagram. How long will it take 10 points to complete the project? Crash the project until the resources available for crashing. Activity Normal Crash Immdediate time Time Normal Cost Crash Cost predecessor (3) (Weeks) (Weeks) 4 3 2000 2600 2 1 2200 2800 3 3 500 500 A 8 4 2300 2600 B 6 3 900 1200 3 2 3000 4200 D.E 4 2 1400 2000 A B D E F G - Your