Question: From the data above, try to determine: a. Make a Network diagram, determine the critical path and the time required b. If the activity on

From the data above, try to determine: a. Make a Network diagram, determine the critical path and the time required b. If the activity on the critical path which has the longest time is accelerated by 3 weeks, what consequences will arise? first row in the column is activity and second row is the time(week)

From the data above, try to determine: a. Make a
6-8 1-2 Aktivitas Waktu(minggu 2-3 2-4 11 4 3-5 4-6 5-7 1 7 2 7-8 5 7-9 1 8-91 9-10 10 5 7 6