Question: From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many

From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?

From the following information, develop an AON project network. Complete the forward

\begin{tabular}{clcc} ID & \multicolumn{1}{c}{ Description } & Predecessor & Time \\ A & Survey site & None & 4 \\ B & Excavate site & A & 4 \\ C & Install power lines & B & 4 \\ D & Install drainage & B & 1 \\ E & Pour foundation & C, D & 2 \end{tabular} \begin{tabular}{|l|l|} \hline \multicolumn{2}{|l|}{} \\ \hline The project will take & days. \\ \hline The critical path is & \\ \hline The late start on Activity C is & days. \\ \hline The slack on Activity C is & days. \\ \hline The slack on Activity D is & days. \\ \hline The early start on Activity E is & days. \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!