Question: From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many
.png)
ID Description Predecessor Time Survey site Install drainage Install power lines Excavate site Pour foundation None B, C
Step by Step Solution
3.38 Rating (157 Votes )
There are 3 Steps involved in it
The project will take 14 days 0 A 2 0 Survey ... View full answer
Get step-by-step solutions from verified subject matter experts