Question: From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many

From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take? Attach or insert your AON network. You may use MSP to check your work, but your submitted file should be similar to that shown in figure 6.8 of Larson & Gray.

ID

Description

Predecessor

Time (days)

A

Survey site

None

2

B

Install drainage

A

5

C

Install power lines

A

3

D

Excavate site

B, C

4

E

Pour foundation

D

3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!