Question: From the following information, draw a project network, identify the critical path, how long will this project take? ID Duration Predecessor A 2 None B

From the following information, draw a project
From the following information, draw a project network, identify the critical path, how long will this project take? ID Duration Predecessor A 2 None B 4 A.E C 6 D 3 B, C E 7 None F 2 E G 1 F, D Select one: a. 10 b. 12 C. 11